The Foundation of a Sky Scraper

How Hollow Steel Piles, Compressed and Concrete Are Employed to Make a

Foundation

Rapidity of building construction is of primary importance in every

city of metropolitan size. When real estate is sold at the rate of

several hundred dollars a square foot it is self-evident that time is

indeed money. The delay of a few days in completing a structure may

deprive the owner of the chance of earning thousands in rental money.

Because of the excessive depth of an open caisson, the completion of

a foundation may be delayed for months. Hence the building may not

be completed until the renting period has passed and the owner must

wait an entire year before he can expect any financial return on his

investment.

Because rapidity is so essential in city building construction the

method of first sinking an open pit to rock in providing a foundation

has been displaced to a large extent by a system in which heavy hollow

steel piles are employed in clusters to support a building. The hollow

piles are driven through quicksand to rock, cleaned out and ultimately

filled with concrete.

~PILES ARE DRIVEN DOWN TO SOLID ROCK~

In this method of constructing foundations, which is illustrated,

hollow steel piles are driven in the well-known manner down to solid

rock. The steel pile sections vary in length from 20 feet to 22 feet,

and in diameter from 12 inches to 24 inches. If the ground is to be

penetrated to a depth greater than 22 feet, the sections of piling

are connected by means of a sleeve in such manner that a watertight

joint is formed. Under a pressure of 150 pounds to the square inch a

jet of compressed air is then employed to blow out the earth and water

contained within the shell. A spouting geyser of mud rising sometimes

to a height of 150 feet, and occasional large pieces of rock blown

up from a depth of 40 feet below the ground, bear testimony to the

terrific force of the air blast.

[Illustration: THE PILES ARE ABOUT TWENTY-TWO FEET LONG. IF GREAT

DEPTHS ARE TO BE REACHED SECTIONS OF PILING ARE JOINED TOGETHER BY

MEANS OF A SLEEVE.]

When the shell has been completely cleaned out by means of the blast

of compressed air, the exposed rock can be examined by lowering an

electric light. Steel sounding rods are employed to test the hardness

of the rock and to detect the difference between soft and hard bed

rock. After the piles in each pier have been cleaned out, they must

be cut off at absolutely the same height--sometimes a very difficult

task when there is little room. The oxy-acetylene torch is used for

the purpose, the intensely hot flame cutting off the steel almost like

butter at the exact elevation desired.

[Illustration: CUTTING STEEL PILES WITH A HOT FLAME